""If we'd only known how difficult it would be, although, of course, we didn't think it would be easy, so we're very proud of what we've been able to achieve.""
""Like many others in Ireland at the time, or in Dublin particularly, we had our deposit handed back to us. We had to get creative or turn our focus elsewhere.""
""The sustainable efforts behind microgrid switch-on include an energy centre that supports the 54MW already in place and will support the full 110W in a few years' time.""
The microgrid-powered datacentre project in Dublin has taken seven years to develop, with significant construction in the last two to three years. The project faced challenges, including the denial of a grid connection and the need for creative solutions to power the datacentre. The first datacentre, DUB01, is set to be operational in 2024, with additional datacentres planned. The facility will utilize innovative cooling systems and support advanced technologies, including AI processing, with future expansion plans to increase capacity significantly.
Read at ComputerWeekly.com