Palo Alto feuds with contractor over public safety building - San Jose Spotlight
Briefly

"Despite recent complications and ongoing disputes involving the main contractor, Swinerton Builders, city officials expect most of the work to be completed by the end of this month, allowing staff to start occupying the building in January 2025."
"The council had twice voted to add $1 million to the contingency funds, but that money was nearly depleted by November. Public Works Director Brad Eggleston noted in a report earlier this month that the money was used on change orders relating to smoke control in the detention area, sally port coiling doors and ADA improvements."